 CRITICAL PATH ANALYSIS

Date:July 1, 1999

This is a USER RPL program written by 	GEORGE SARKODEE
P.O. BOX DS 1618
DANSOMAN
ACCRA,GHANA
W.AFRICA

E-mail : gsark@hotmail.com


I wrote this program about two years ago, but then I did not have Internet access to upload.

For all your Time Management on any project, NETWRK will do all the Network Analysis and fish out the Critical Path for you.  It will also compute all the total and free floats for you.

The ff. Files are:-
NETWRK		(1105 bytes)
PRTY			(131 bytes)
FISH			(215 bytes)
FLOAT		(280 bytes)
OTPT			(1629 bytes)

The grobs are:-	
1)	INTRO		(1108 bytes)
2)	DISPL		(445 bytes)

Total no. of bytes:		5908 bytes

HOW TO RUN IT

Execute NETWRK from the menu.
Always enter link data in the correct order..................... VERY CAREFULLY.
It must be in the "lower to upper" form, and from node to node (also in order; i.e Lower to upper)
Simply put, Enter the lower numbered destination before the upper one for any given start node.

Eg.     	1-2
2-3
2-4
3-4

3-5
4-5
5-6






The Total duration of the Project will be indicated at the top right corner in PICT.
The Critical Path is shown in the second line in PICT.
All critical path links are hi-lighted.
When you exit PICT, the critical path is stored in a variable "CP" whereas the total project duration is stored in "tm".

I hope this proves useful to some of you 48 guys out there.
I haven't had much time to learn Assembly language and ML yet, however any comments or suggestions are welcome.

Please direct 'em to the above e-mail address.

I just heard about the HP49 but STILL, I won't let go of my 48. Peace.!!!!!!